As a general contractor, we are carrying out an investment in Chojnice: a two-story production building designed to fully utilize the available plot.

Challenge

  • Limited expansion possibilities and the need to ensure high load-bearing capacity of the ceilings and fire safety.

Solutions used:

  • High-load-bearing ceiling – 950 kg/m²
    A hollow-core ceiling with a composite floor was used, ensuring high rigidity and the ability to withstand significant operational loads.
  • Second floor for a racking system
    The design takes into account the weight of the racks and stored materials, which required precise selection of structural solutions and static analyses.
  • Prefabricated freight elevator shaft
    The second floor will be served by a modern freight elevator in a prefabricated shaft, enabling quick and safe transport of materials between levels.
  • Fire protection
    The building will be equipped with fire walls and a sprinkler system, in accordance with applicable safety regulations and standards.

Effect

  • A modern, efficient and safe industrial facility that makes maximum use of limited space.

Other news

23.10.2025

New investment in Kościan – construction is starting!

We are implementing a new project involving the construction of a production/warehouse hall, an office and social building on the site of an existing production plant.

13.10.2025

When every hour counts – modernization of the roof at an operating production plant in Chojnice

Modernizing the roof of an existing production facility isn't just about construction. It's a precise operation—time-constrained, demanding, and with zero margin for error.