Two-story production facility – maximum functionality in a limited space

06.10.2025

As a general contractor, we are carrying out an investment in Chojnice: a two-story production building designed to fully utilize the available plot.

Challenge

  • Limited expansion possibilities and the need to ensure high load-bearing capacity of the ceilings and fire safety.

Solutions used:

  • High-load-bearing ceiling – 950 kg/m²
    A hollow-core ceiling with a composite floor was used, ensuring high rigidity and the ability to withstand significant operational loads.
  • Second floor for a racking system
    The design takes into account the weight of the racks and stored materials, which required precise selection of structural solutions and static analyses.
  • Prefabricated freight elevator shaft
    The second floor will be served by a modern freight elevator in a prefabricated shaft, enabling quick and safe transport of materials between levels.
  • Fire protection
    The building will be equipped with fire walls and a sprinkler system, in accordance with applicable safety regulations and standards.

Effect

  • A modern, efficient and safe industrial facility that makes maximum use of limited space.

Other news

06.03.2026

The investment project for NDL Industrial Sp. z o.o. in Motaniec is entering its next, intensive phase.

Thanks to the efficient coordination of construction teams and ongoing monitoring of key milestones, we carry out earthworks, foundation works, reinforcement works, and the assembly of the building's prefabricated structure.

02.12.2025

Step by step towards the perfect floor!

Creating a durable and solid industrial floor is one of the most important stages of hall construction.